Ipari technológiák-03

Successful Handover of the Renewable Energy Plant

2013. December 09. Monday
Our firm has realized as EPC-M main contractor the BIO2 project Pécs. This is one of the largest biomass power plant in Europe. This BIO2 Project meant the biggest challenge for the Kraftszer Team’s life in the last years.

Successful handover in Dunamenti Power Plant

2013. September 30. Monday
According to the requirements of Client the 22 t/h capacity steam boilerhouse was successfully handed over at the end of September 2013.

Manufactory expansion in AUDI

2013. August 06. Tuesday
Audi – accordingly its saying “Vorsprung durch Technik” - extended its test-shop area by energy efficient heatpump equipment (70 KW) using geothermal.

Steam boiler arrival at the installation site

2013. June 21. Friday
Project came in phase of the technological realization, within the installation of the supply container, then after the erection of the steel structure and chimney, at the end of June 2013 has the 22 t/h BOSCH steam-boiler arrived at the site of Dunamenti Power Plant, where under severe security measures got to its final place.

Execution of a complete Boiler House for district heating in Dunamenti Power Plant

2013. June 12. Wednesday
Kraftszer Ltd. gained a new tender at Dunamenti Power Plant, where new hot water boilers will be installed for district heating supply.

Installation of a steam boiler block in the Dunamenti Power Plant

2013. April 26. Friday
Installation phase of a new steam boiler block has begun at Dunamenti Power Plant. Kraftszer Ltd. as main contractor provides turnkey operation of a 22t/h boiler room. As part of the architecture, mechanical engineering, electrical and I&C tasks our company is also responsible for building permit plans, engineering, site construction, complete installation and commissioning. The boiler room will be able to produce 22 t/h steam overheated to 300 0C at 15 barg over-pressure, its heat demand will be ensured by a Bosch UNIVERSAL UL-SX 22.000 steam-boiler and supplemental units. Expected date of completion of the project is 30 September 2013.

COGEN Hungary annual conference

2013. April 02. Tuesday
COGEN Hungary hold its 16th annual conference on 20-21 March in Balatonalmádi, Hotel Ramada.

Another conveyor belt started operating in the new biomass unit of Pécs Power Plant

2013. January 23. Wednesday
This January, the construction of the 35-MWe capacity new biomass unit of Pécs Power Plant has passed a significant milestone: after the successful testing and fine-tuning activities, now there are two conveyor belts carrying agricultural by-products from the fuel storage hall to the furnace of the boiler.

New successful project at Mercedes-Benz Manufacturing Hungary Ltd.

2013. January 21. Monday
On November 2012 Kraftszer Ltd. has completed a new successful project on the site of Mercedes-Benz Manufacturing Hungary Ltd.

ALPIQ AAT workshop in CERN

2012. November 13. Tuesday
CERN hosted the workshop regularly organised by ALPIQ Anlagentechnik GmbH (AAT), where the associates of the member companies of the concern could personally gain insight into ongoing scientific research.
Erőművek, ipari energetikai- és technológiai létesítmények kivitelezője