BorsodChem- extension of high-, medium and low pressure steam network

BorsodChem- extension of high-, medium and low pressure steam network

任务:

Complete installation of steam pipelines, steam reduction and distribution system.

Customer BorsodChem

Therm Co. Content Prepare the licensing and implementation design. The complete installation of the establishment with procurement of goods and equipment, cleaning, blow down commissioning.

Description of the establishment :

BC Co. has expanded its steam producing and distributive capacity to supply steam for its newly built factories. The reconstruction of the factory section Steam-I and the connection to the source site will result in a new, 160 t/h distributive capacity, which will supply the main producing areas together with Steam-III factory section on the plants nr. 1 and 3. Implementation - Establishment of a steam collecting system on the high pressure steam collector next to the boiler for collecting the steam coming from BC power plant (50 t/h) and the newly built 110 t/h capacity natural gas/fuel–burning boiler (30 barg, 370°C fresh steam product) Installation of the steam pipeline system from the steam distribution until the steam receive station next to the factory section Steam-III with pipe bridges and fittings (app. 1200 meter long with 4 parallel pipelines) Installation of steam receiver/reducing and steam distribution system in the factory section Steam-III Installation of the whole steam distribution pipeline system that reaches the consumers, with pipe bridges and fittings Installation of auxiliary system (unloading, deaerator and silencer system)

客户

BorsodChem Therm Kft.

地点

3700 Kazincbarcika

开始运营

2008-01-01

Erőművek, ipari energetikai- és technológiai létesítmények kivitelezője