Budapest Power Plant, Kelenföld Power Station - installation of the water treatment plant (WTP)

Budapest Power Plant, Kelenföld Power Station - installation of the water treatment plant (WTP)

任务:

Installation of the new water treatment plant using UP-CORE technology for producing basic and fine desalted water Customer Budapest Power Plant.

Content:

Designing, preparing licensing plans, building, installing and commissioning of the new water treatment by Kraftszer Ltd. as the Main Contractor, detailed below:

- design works

- Piping and instrumentation,

- permit and consent procedures (authorities),

- engineering, I&C, transmission design,

- production, delivery, installation,

- commissioning

- training, final report.

Description of the establishment:

By using 3*70 t/h capacity cation/anion exchangers the new WTP generates basic desalted water from the raw Danube water with calcariferous pre-emollient. The new WTP generates additional fine desalted water by using 2*70 t/h capacity mixed bed exchangers. (In the course of the desalting procedure the UPCORE technology is being used.)

客户

Budapesti Erőmű Rt.

地点

1117 Budapest, Budafoki út 52.

开始运营

1995-01-01

Erőművek, ipari energetikai- és technológiai létesítmények kivitelezője