Glaxo Smith Kline Vaccine Production Plant, Gödöllő

Glaxo Smith Kline Vaccine Production Plant, Gödöllő

任务:

Implementation of all of the service (Black Utilities) systems of the new vaccine plant, from the design phase through construction to commissioning.

The task of Kraftszer Kft. was to deliver, install and position all machinery and equipment as follows:

Full-scope implementation of machinery and equipment piping according to media: preparation of main line, path, isometric drawings based on layout drawings by levels approximately 25,000 m of pipelines (as per various pipe categories ranging from zinc-coated to stainless and hot strength materials) approx.

21,000 fittings and 4,500 assemblies (screwed, flanged) were installed almost 14,000 welded joints were prepared Putting the system into service and commissioning: pressure tests by systems, media (approx. 160 pressure circuits) construction of temporary work-arounds, cleaning and blow-down works supervision while units were put into service, operation

Recording of IQ/OQ data sheets

Customer: Foster Wheeler Italia, World Service Italy

客户

Foster Wheeler Italia, World Service Italy

地点

2100 Gödöllő

Erőművek, ipari energetikai- és technológiai létesítmények kivitelezője