任务:
Our task:
Implementation of systems servicing the new combined cycle power plant (design, construction, commissioning).
Scope of supply:
- Gas turbine lube oil system
- Anti icing system
- Steam system 16 bar
- Steam system 42 bar
- High pressure steam system
- Water injection system
- Condensate system
- Compressed air system
- Closed cooling water system
- Drain system
- Fuel gas system
- Fuel oil system
- Hot water system
- Make up water, drain system.
Design, assembly and commissioning of all yard area pipeline systems:
- Steam systems (high pressure, 42 and 16 bar)
- Other service systems (serving gas and steam turbines)
Full-scope implementation of oil supply, as well as water refill, escape water, discharge and hot water systems: Mechanical, electrical and I&C design, construction and commissioning Design, manufacturing and licensing of 300 m3 oil tank Oil supply system from the oil pump station to the auxiliary boilers’ assembly rig Delivery, installation, setting up of tanks, pumps, heat exchangers, appliances, instruments and other equipment Putting all systems online and their commissioning: Pressure tests for each system and type of media Construction of temporary work-arounds, cleaning and blow-down works Supervision while units were put into service, operation Recording of IQ/OQ data sheets
Customer: TVK
客户
TVK Erőmű Kft.
地点
3580 Tiszaújváros
开始运营
2004-01-01